Allegheny Land Trust Logo Allegheny Land Trust
     Helping local people save local land

 

AMD Treatment System Construction Photos

Click on any photo for a larger version.

Mid-March 2009

By mid-March, a by-pass structure had been constructed at the discharge site to capture the mine outflow and eventually divert it to the distribution pipes.  (View a schematic of the AMD Treatment System.)

By-pass structure.
Mine discharge water continues to flow. . .

Drained beaver pond.
. . . untreated to Chartiers Creek .

By-pass structure.
Eventually, this port of the by-pass structure will
divert outflow to Pond #1 (aeration pond).

Construction materials.
Concrete forms for troughs through the berms and pipe
that will carry water to the waterfall spillway.


Heavy machinery has been moving earth to form the aeration and settling ponds.  The berm outlines are beginning to take shape.

Working backhoe.
A large backhoe creates a ledge for the
aeration waterfall in Pond #1.

Working bulldozer.
A bulldozer moves earth to form berms
for the settling ponds.

Curved berm.
The outer circular berm of Ponds #2
through #5 is clearly visible.


Early April 2009

Recent rains made earth-moving difficult, so workers concentrated on constructing the distribution pipe which will carry mine water from the discharge site to the aeration waterfall at Pond #1.  (View a schematic of the AMD Treatment System.)

Distribution pipe installation.
Workers assemble the distribution pipe. . .

Distribution pipe installation.
. . . that will carry water to the first pond.

View of distribution pipe.
The pipe runs along the base of the hill
and eventually will be buried.

Setling pond berms.
Meanwhile, the settling pond berms
continue to take shape.


Late May 2009

The project is really beginning to take shape.  (View a schematic of the AMD Treatment System.)

Distribution pipe connection.
The connection to the aeration waterfall is almost complete.

Completed settling ponds.
The berms of the pie-shaped settling ponds are complete.

Wetlands under construction.
Grading of the wetlands area is almost compete.

Geese in iron oxide contaminated pond.
Soon these guys will have a much cleaner environment.


July 17, 2009

Mine discharge water has been diverted into the treatment system and begins to fill the ponds.  (View a schematic of the AMD Treatment System.)

Aeration waterfall.
AMD water is diverted to the aeration waterfall . . .

Aeration pond.
. . . and the settling ponds begin to fill.

Settling Pond #2 filling.
Cleaner water flows from the aeration
pond to the first settling pond.


July 24, 2009

Only one week later and the AMD treatment system is working, with clearly visible results!  (View a schematic of the AMD Treatment System.)

Aeration waterfall.
Aeration of the mine discharge allows iron dissolved
in the water to form iron oxide which then
falls to the bottom of the settling ponds.

View of Settling Ponds #2 and #5.
Pond #2 on the left and Pond #5 on the right
clearly show how the four settling ponds
remove iron oxide from the mine outflow.

Discharge from Pond #5 to wetlands.
Clear water from Pond #5 flows out to the wetlands. . .

Wetlands.
. . . where additional cleaning occurs.

Clear mine discharge water.
Clear AMD discharge water flows out of the treatment system. . .

Clear discharge water leaves treatment system.
. . . to the old discharge channel and into Chartiers Creek.


Return to the AMD Project page

Allegheny Land Trust